Watt criticises Queensland environmental law review

Watt criticises Queensland environmental law review
Spread the love

Arabic version: وات ينتقد مراجعة قوانين البيئة في كوينزلاند

According to ABC News, Queensland’s Productivity Commission will take an extra three months to complete its assessment of how federal environmental law changes affect the state’s infrastructure pipeline. An interim report said several reforms had not yet been drafted, released for consultation or implemented, leaving limited observable evidence of their full effects.

Federal Environment Minister Murray Watt criticised the Queensland government’s review, calling it a “political stunt”. He said other states were preparing agreements with the Commonwealth intended to reduce red tape and accelerate project approvals, while Queensland had chosen to wait for a Productivity Commission report on laws that had not fully begun. Watt said Queensland was “no longer the smart state, it’s the slow state”.

Queensland Treasurer David Janetzki said the interim findings were “startling” and argued that Canberra’s changes were adding cost and delay. He cited findings that federal environmental approvals had taken an average of 1,150 days in Queensland and cost up to $7.7 billion annually. The report noted, however, that those figures predated implementation of the 2025 reforms.

Janetzki rejected the characterisation of the final report as delayed, describing the change as an extension. He said the inquiry was intended to help Queensland negotiate with the federal government. The 15-month inquiry’s cost was not disclosed; the treasurer said it was covered within the Commission’s $6.7 million annual budget.

The interim report also identified deficiencies in the continuing reforms, including limited consultation on some elements. It said expanded land-clearing requirements could capture small and family farming businesses, estimating an annual cost to Queensland agriculture of between $14 million and $41 million. Stakeholders can provide feedback before the final report is delivered in July next year.